SiteWright — Built for the meetings that build the project
SJ

Trackers

RFIs, submittals, constraints, and impacts detected during meetings.

IDTitleResponsibleRefDueStatusMeeting
RFI-021Curtain wall anchorage detail at column line CArchitectA-501May 20, 2026
Open
OAC — May 14
RFI-022MEP roof penetrations above mech roomMEP EngineerM-302May 12, 2026
Answered
MEP Coord — May 12
RFI-023Slab edge condition at balcony transitionStructuralS-210May 22, 2026
Open
OAC — May 14
RFI-024Door hardware spec for Level 3 stairArchitect08 71 00May 24, 2026
Draft
OAC — May 14