| Action | Owner | Company | Due | Priority | Status | Meeting | Section |
|---|---|---|---|---|---|---|---|
Provide updated rebar delivery schedule for Level 4 | Brian Smith | Steel Erectors | May 21, 2026 | High | Open | OAC — May 14 | Schedule |
Submit fall protection plan for Level 5 roof edge | Mike Kim | Northline GC | May 22, 2026 | High | In Progress | OAC — May 14 | Safety |
Confirm 480V power capacity for tower hoist relocation ● Overdue | David Chen | Central Electric | May 18, 2026 | Medium | Open | OAC — May 14 | Procurement |
Coordinate 5-inch pipe adjustment above corridor B | Buss Mechanical | Buss Mechanical | May 20, 2026 | Medium | Open | MEP Coord — May 12 | Coordination |
Distribute updated door schedule Rev C | Sarah Johnson | Northline GC | May 19, 2026 | Low | Blocked | OAC — May 14 | Submittals |
Owner review of alternate ceiling grid vendor | Owner's Rep | Riverside Holdings | May 24, 2026 | High | Open | Owner Update — May 8 | Owner Decisions |