Provide updated rebar delivery schedule for Level 4
Brian SmithSteel ErectorsMay 21, 2026
High
Open
OAC — May 14Schedule
Submit fall protection plan for Level 5 roof edge
Mike KimNorthline GCMay 22, 2026
High
In Progress
OAC — May 14Safety
Confirm 480V power capacity for tower hoist relocation
● Overdue
David ChenCentral ElectricMay 18, 2026
Medium
Open
OAC — May 14Procurement
Coordinate 5-inch pipe adjustment above corridor B
Buss MechanicalBuss MechanicalMay 20, 2026
Medium
Open
MEP Coord — May 12Coordination
Distribute updated door schedule Rev C
Sarah JohnsonNorthline GCMay 19, 2026
Low
Blocked
OAC — May 14Submittals
Owner review of alternate ceiling grid vendor
Owner's RepRiverside HoldingsMay 24, 2026
High
Open